单选] 在一次项目审查会议中,项目团队遇到了一个关键的技术性问题,会在下一次评审会议中进行讨论。项目经理应该邀请哪些人参加下一次会议,以便得出有效的行动措施?During a project review meeting, the project team encountered a critical technical issue that would be discussed at the next review meeting. Who should the project manager invite to the next meeting so that effective action can be taken?
A、内部团队Internal team
B、最终用户团队End user team
C、管理团队Management team
D、项目团队Project team
发布时间:2024-11-21 10:59:27