If the suspension is for a reason other than on the contractor’s side, then:
A、thecontractormaynotifyaclaim;
B、ifthesuspensioncontinuesformorethan84days,thecontractormayrequestpermissiontoproceed;
C、iftheengineerdoesnotgivepermissiontore-startwithin28days,thecontractormayterminatethecontract;
D、thecontractorshallresumenormalworkingactivitiesassoonasisthenreasonablypossible